Page 9 - 251119_BJ_ME-Journal_14_digital
P. 9

Solution


                                                                               HVACR system is isolated by the area it serves.
                                                                               Phase 1 could have had its own BACnet/IP ring,
                                                                               phase 2 its own as well as phase 3. As each
                                                                               area had been completed, all devices could
                                                                               have  been  discovered  and  commissioned  with
                                                                               the redundancy of the BACnet/IP ring. As the
                                                                               following phases were added, each would
                                                                               have its own ring to connect to the supervisor.
                                                                               As issues arise from the construction or
                                                                               commissioning process, only areas involved
           © ABB
                                                                               would have been exposed, leaving the existing
                                                                               networks unaffected.
          BAS stopping and starting the fans. Providing   public. In a case like this, ABB confirmed the new
          this information to the controls contractor, they   firmware did not negatively impact the network  While it is inconvenient for the facilities team
          were able revise the programming and use the   and existing devices as well as working with the  working to understand where issues are to
          BACnet point BV0 running status for each drive   BAS to discover the new BACnet/IP points and  trace down with the single ring network, the
          status, providing a better design of the fan array.  confirm they were reading as expected.  advantages of the multiple  BACnet/IP ring
                                                                               topology could have been  leveraged to  make
          Finally, to help offset the electrical demands   BACnet/IP Connectivity  the system more robust during construction,
          of the facility, 332 kW of solar panels are also                     commissioning and possibly future expansions.
          installed on the building roof. After the first   Tying together all the HVACR equipment, lighting
          year of operation, the solar system generated   controls, monitoring and alarms is the ABB  Building Analytics
          413 MWh of  power for  the facility,  saving   Smart Buildings INTEGRA building automation
          approximately 640,000 pounds of CO . Through   system connected to each piece of equipment  With the focus on energy and operational
                                   2
          the integration of the BAS, a future phase of the   over BACnet/IP. Ring topology was implemented  efficiency, the building’s design roadmap is to
          project  will  combine  data  from  the  integrated   looping around the building from the supervisor  showcase and leverage analytics to continuously
          power meters with the power factor correction   panel through the chiller plant and AHU, to the  optimize the building’s performance. Using
          capabilities of active front end drives to further   VAV boxes and terminal controllers, out to the  the  BAS  and  equipment  communicating  over
          improve building energy efficiency.  production area RTUs as well as the R&D space.  BACnet/IP, the monitoring data, trends, active
                                            While the final  design  may work with many  setpoints, energy  consumption and  more is
          Redundant Equipment Benefits      devices all interconnected, this topology leads to  continuously  collected  to  understand  how  the
                                            difficulties during the phased construction.  building is operating. From the chiller’s geo-loop
          The office area central plant design includes                        energy meter, to the building’s electrical power
          N+1 pumps programmed from the BAS to rotate   For example, with two links of the  BACnet/IP  meters,  energy data available  from  the  VFDs,
          operation and provide redundancy in case of any   cabling leaving the supervisor’s rapid spanning  the lighting system occupancy sensors, the VAV
          failure or planned down time for maintenance.   tree protocol ethernet switch, the phase 3  zone temperature sensors and the rooftop solar
          To further take advantage of this design, ABB’s   R&D area was incomplete with devices not  energy being produced, the information will be
          R&D group can test new firmware versions in a   installed closing the link in the ring. Several  used to adjust temperature or pressure setpoints
          live system before release. For example, when a   production area RTUs have needed additional  and occupancy schedules to reduce energy
          new addition to the BACnet/IP fieldbus adapter   commissioning and when these units have  needs without negatively impacting office space
          was ready, the adapter was applied to drives in   been shut down, many other devices go offline  comfort or production area requirements.
          the mechanical room for real world verification   as well. While this may be common during the
          and testing, before making it available to the   construction process, phase 2 included ramping  This new building was designed to accommodate
                                            up manufacturing production. It was becoming  ABB’s current needs and future growth, as the
                                            more critical for the HVACR equipment to  products manufactured in this facility support
                                            be online, not only for occupancy but also  the HVACR industry’s demand for efficiency and
            ABOUT THE AUTHOR                production quality control.        sustainability. From the flexible workspaces in the
                                                                               offices, the adaptable production area utilizing
            Starting with ABB in 2022, I have been   As a lesson learned on the project, an ideal  advancements in automation, and the efficient
            working in the HVAC industry since 2015.   opportunity for  BACnet/IP and a phased  HVACR systems with  BACnet integration, the
            My background has been HVAC equipment   construction would have been to implement  building meets today’s demand while being
            and Building Automation System design,   several network rings. Each phased construction  flexible to tackle tomorrow’s challenges.
            programming, implementation, startup,
            commissioning, training and support. With
            ABB, I am an HVACR Application Engineer
            and I support our Channel Partners with
            complex drive applications and answer             Will Brewer
            questions assisting with variable frequency       HVACR Application Engineer | ABB
            drives in the HVACR market.                       will.r.brewer@us.abb.com | www.abb.com/global/en/areas/motion/drives




                                                                                                             9
                                                                                  BACnet Middle East Journal 14 11/25 9
   4   5   6   7   8   9   10   11   12   13   14